據(jù)OE網(wǎng)站3月17日報(bào)道,西班牙可再生能源巨頭Iberdrola已與Cosmo Eco Power和Hitz達(dá)成協(xié)議,共同開發(fā)位于日本西北部青森縣的600兆瓦 Seihoku-oki風(fēng)力發(fā)電項(xiàng)目,為其日本投資組合增加了另一個(gè)海上風(fēng)力發(fā)電項(xiàng)目。
正在開發(fā)的Seihoku-oki海上風(fēng)電場將進(jìn)入日本政府計(jì)劃在今年至2022年之間進(jìn)行的第二輪發(fā)電量拍賣。Iberdrola表示,在交易完成后(需要獲得通常的監(jiān)管批準(zhǔn)),該項(xiàng)目將由Iberdrola和Cosmo Eco Power牽頭,并與Hitz擁有類似的投票權(quán)。
Iberdrola稱,Seihoku-oki的交易發(fā)生在收購日本開發(fā)商Acacia可再生能源公司100%股權(quán)的6個(gè)月之后。Acacia可再生能源公司在日本南部擁有3300兆瓦的海上風(fēng)力管道。這是Iberdrola自2020年初以來簽署的第六份海上風(fēng)電協(xié)議。
Acacia可再生能源公司有兩個(gè)海上風(fēng)電場正在開發(fā)中,總發(fā)電能力為1200兆瓦,可能在2028年投入使用。此外,該公司還有四個(gè)管道項(xiàng)目,總發(fā)電能力為2100兆瓦。這六個(gè)項(xiàng)目將由Iberdrola與麥格理(Macquarie)的綠色投資集團(tuán)(GIG)共同開發(fā)。
Iberdrola表示,這將使Iberdrola在該國的管道達(dá)到3900兆瓦,并將在政府宣布的第2、3、4輪海上拍賣中競爭。到2040年,日本海上風(fēng)電市場的發(fā)電量預(yù)計(jì)將達(dá)到3萬-4.5萬兆瓦。
目前日本的海上風(fēng)電裝機(jī)發(fā)電量約為70兆瓦,但預(yù)計(jì)到2040年將達(dá)到45吉瓦。
郝芬 譯自 OE
原文如下:
Iberdrola Enters 600MW Seihoku-oki Offshore Wind Project in Japan
Spanish renewable energy giant Iberdrola has added another offshore wind project to its Japanese portfolio as it has agreed with Cosmo Eco Power and Hitz to jointly develop the 600MW Seihoku-oki wind project in Aomori prefecture, in the northwest of the country.
The Seihoku-oki offshore wind farm, under development, will enter round 2 of the capacity auction planned by the Japanese government between this year and 2022. Following the transaction - subject to the usual regulatory approvals - the project will be led by Iberdrola and Cosmo Eco Power, with similar voting rights, together with Hitz, Iberdrola said.
Iberdrola said that the Seihoku-oki deal took place six months after the acquisition of 100% of Japanese developer Acacia Renewables - which has a 3,300-MW offshore wind pipeline in the south of the country. It is the Iberdrola's sixth offshore wind agreement since early 2020.
Acacia Renewables has two offshore wind farms under development, with a combined capacity of 1,200 MW, which could be operational by 2028. It also has four other projects in the pipeline, with a total capacity of 2,100 MW. These six projects will be developed by Iberdrola together with Macquarie's Green Investment Group (GIG).
"This brings Iberdrola's pipeline in the country to 3,900 MW and will be competing in rounds 2, 3, and 4 of the offshore auctions announced by the government. The Japanese offshore wind market is expected to reach 30.000 - 45.000 MW in operation by 2040," Iberdrola said.
Japan's installed offshore wind capacity currently stands at around 70 MW but is expected to reach 45GW of installed offshore wind capacity by 2040.
標(biāo)簽:海上風(fēng)電場
相關(guān)資訊